Project Number | Project Name | Agency/Building/Institution | Project Budget | Project Manager | Notes | Deadline for Submissions (Due by 12:00 PM) | Selected A/E |
---|---|---|---|---|---|---|---|
21K1P | 21K1P - Chiller Replacement, Central Heating Plant | University of Wisconsin/UW-Milwaukee | $18,500,000 | Robert Otremba | Asbestos Abatement Design Services Only | 05/31/2024 | |
22E1L | 22E1L - Polk Library Facility Renewal | University of Wisconsin/UW-Oshkosh | $120,000,000 | Pete Kolaszewski | Commissioning Services AND Asbestos Abatement Design Services (separate solicitations) | 05/31/2024 | |
22G2W | 22G2W - New Student Dormitory | Department of Public Instruction/School for the Deaf, Delavan | $25,000,000 | Caleb Janus | Environmental Assessment Only | 05/31/2024 | |
23G1C | 23G1C - MMHI Utility Improvements | Department of Health Services/Mendota Mental Health Institut | $19,920,000 | Troy Cunat | Environmental Assessment Only | 05/31/2024 | |
23K2J | 23K2J - WMHI Utility and Service Tunnel Improvements | Department of Health Services/Winnebago Mental Health Instit | $44,043,000 | Robert Otremba | Environmental Assessment AND Asbestos Abatement Design Services (separate solicitations) | 05/31/2024 | |
24B2F | 24B2F - Well 5, Les Voight Fish Hatchery | Department of Natural Resources/South Shore Lake Superior Fish | $928,000 | Kathy Kalscheur | 05/31/2024 | ||
24D2T | 24D2T-Road and Campground Improvements | Department of Natural Resources/Governor Dodge State Park | $4,997,000 | Peggy Wischhoff | 05/31/2024 | ||
24D3D | 24D3D-Dane County Trail Improvements | Department of Natural Resources/Statewide | $889,000 | Sally Shumaker | 05/31/2024 | ||
24D3I | 24D3I-NW Wisconsin - State Park Roads Improvement | Department of Natural Resources/Amnicon Falls State Park | $2,271,300 | Reiny Yahnke | 05/31/2024 | ||
24D3J | 24D3J-Northern Buildings Package | Department of Natural Resources/Big Bay State Park | $2,098,000 | Mike Bowman | 05/31/2024 | ||
24D3K | 24D3K-Statewide Water Fountain Improvements | Department of Natural Resources/Devils Lake State Park-Iansr | $477,700 | Pete Kolaszewski | 05/31/2024 | ||
24D3M | 24D3M-East Chiller Plant Chiller Replacement and Installation | University of Wisconsin/UW-La Crosse | $6,564,000 | Troy Cunat | 05/31/2024 | ||
24D3R | 24D3R-Gordon Dining Dishroom Renovation | University of Wisconsin/UW-Madison | $1,500,000 | Evan Quilling | 05/31/2024 | ||
24D3T | 24D3T-Witte Hall Tower A HVAC System Improvements | University of Wisconsin/UW-Madison | $1,775,500 | Doug Schorr | 05/31/2024 | ||
24D4D | 24D4D-Witte Hall Tower B HVAC System Improvements | University of Wisconsin/UW-Madison | $1,775,500 | Doug Schorr | 05/31/2024 | ||
24D4S | 24D4S-Well Improvements Statewide Properties | Department of Natural Resources/Kinnickinnic State Park | $991,200 | Kathy Kalscheur | 05/31/2024 | ||
24D4Z | 24D4Z-Dane County Buildings | Department of Natural Resources/Statewide | $1,654,000 | Dave Hoffman | 05/31/2024 | ||
24E5L | 24E5L-Renovation of Dock Facilities | Department of Natural Resources/Rock Island State Park | $3,122,000 | Pete Kolaszewski | 05/31/2024 | ||
24E6F | 24E6F-Boat Launch and Road Improvements | Department of Natural Resources/Peshtigo River State Forest | $7,117,800 | Sally Shumaker | 05/31/2024 | ||
19I1L | 19I1L - Winther Hall Addition and Renovation | University of Wisconsin/UW-Whitewater | $78,489,000 | Jeremy Hall | Environmental Impact Assessment Only | 04/29/2024 | Ayres Associates (0000013801) |
23D1J | 23D1J - Sentry Hall Addition and Modernization | University of Wisconsin/UW-Stevens Point | $76,000,000 | Steve Wenzel | Environmental Impact Assessment Only | 04/29/2024 | Ayres Associates (0000013801) |
23K1K | 23K1K - UWMSN West Campus Electrical Substation Renovation | University of Wisconsin/UW-Madison | $1,686,000 | Cleven McChesney | 04/29/2024 | KFI Engineers (0000134528) | |
24C2A | 24C2A - Roadway Repaving and Various Repairs | Department of Natural Resources/Yellowstone Lake State Park | $1,555,500 | Reiny Yahnke | 04/29/2024 | KL Engineering Inc (0000019434) | |
24C2C | 24C2C-Sanitary Sewer System Improvements | Department of Natural Resources/Interstate Park | $666,700 | Kristine Anderson | 04/29/2024 | Becher-Hoppe Associates Inc (0000013454) | |
24C2D | 24C2D-KMSF Southern Unit Buildings | Department of Natural Resources/Kettle Moraine State Forest-So | $1,015,400 | Jeremy Hall | 04/29/2024 | ZS LLC (0000109166) | |
24C2E | 24C2E-Door County Paving and Trails | Department of Natural Resources/Statewide | $3,176,700 | Pete Kolaszewski | 04/29/2024 | JT Engineering Inc (0000003157) | |
24D2M | 24D2M-Multi-Building Demolition | University of Wisconsin/UW-Eau Claire | $2,558,000 | Mike Bowman | 04/29/2024 | Ayres Associates (0000013801) | |
24D2P | 24D2P-Stovall Hall Forensic Unit Remodel Project | Department of Health Services/Mendota Mental Health Institut | $2,968,000 | Caleb Janus | 04/29/2024 | Kontext Architects LLC (0000005252) | |
24D2W | 24D2W-Roofs, Siding, Windows, Doors, Shed Replacement | Department of Natural Resources/Interstate Park | $765,500 | Jerry Zamzow | 04/29/2024 | Westlund Consultancy LLC (0000150278) |